Navigation Monitoring

Legend

Typical Operations: Remedial operations allow for continuous use of the river with minimal impacts

Control Level: Deviation from the performance standards, although the issue can be easily and immediately mitigated OR a project related navigation complaint is received from the public

Exceedance Level: Remedial activities unnecessarily hinder overall non-project-related vessel movement and create project related navigation impacts OR frequent, recurrent complaints indicating project activities are unnecessarily hindering overall non-project-related vessel movement

Calendar (Please click on data for more information)


Dredging occurred between May 15 - Oct 26, 2009.

View Most Recent Data


<<    Jul 2010    >>
SundayMondayTuesdayWednesdayThursdayFridaySaturday
1
River Operations: Typical
2
River Operations: Typical
3
No Activity: -
4
No Activity: -
5
No Activity: -
6
River Operations: Typical
7
River Operations: Typical
8
River Operations: Typical
9
River Operations: Typical
10
No Activity: -
11
No Activity: -
12
River Operations: Typical
13
River Operations: Typical
14
River Operations: Typical
15
River Operations: Typical
16
River Operations: Typical
17
River Operations: Typical
18
River Operations: Typical
19
River Operations: Typical
20
River Operations: Typical
21
River Operations: Typical
22
River Operations: Typical
23
River Operations: Typical
24
No Activity: -
25
River Operations: Typical
26
River Operations: Typical
27
River Operations: Typical
28
River Operations: Typical
29
River Operations: Typical
30
River Operations: Typical
31
River Operations: Typical

Goal of the Standard

The goal of the navigation performance standard is to avoid unnecessary interference with or the slowdown of vessels unrelated to the cleanup that are within the project area.

The performance standard for navigation requires compliance with the applicable sections of federal and state navigation laws, rules and regulations. It also calls for the following requirements, as needed, to meet the goal of the standard:

  • Evaluating vessel movement
  • Restricting access to work areas and providing safe access around them
  • Keeping mariners informed about scheduled project work that might affect vessel movement
  • Establishing temporary aids to navigation such as signs and buoys to maintain safe and efficient vessel movement, and
  • Scheduling project activities to consider vessel movement

In addition, there will be monitoring of vessel traffic, follow up on complaints, and outreach to mariners on a regular basis. EPA developed and will ensure compliance with the navigation performance standard in consultation with the New York State Canal Corporation (NYSCC) and other appropriate agencies.

While operations are occurring in the east channel of Rogers Island, limited passage of non-project vessels to and from the Fort Edward Yacht Basin will be allowed. To allow such limited passage, a gate has been designed in the silt curtain barrier to be installed at the southern end of the east channel of Rogers Island. Recreational vessels will be able to travel through this gate each day during a 1/2-hour period between the hours of 7 and 9 a.m., and again during a 1/2-hour period between 3 and 5 p.m. The specific 1/2-hour slot within these 2-hour time periods will be determined by the Dredging Contractor.

EPA